| 
                         The Bridge Across 
Millinocket Stream 
                         Jim Barnes - In memory of.........
                         Each base took approximately 8 ½ yards 
                         of cement, which was generously donated by Jeff Goding 
                         of Goding Cement Company. 
                              On August 31st the forms 
                         were stripped off and the area around the bases were 
                         backfilled with the use of the donated backhoes. It was 
                         then that a 60 ton crane donated by Cianbro and a 40 
                         ton crane donated by the Ensor Construction Company 
                         lifted and placed the 18,000 lb. Beams across the 
                         stream and onto the base plates. Many thanks went to 
                         Jim Owens of ENSR and Dave Whitehead and Tom Luckern of 
                         Cianbro on that September 12th.
      
                         When the beams were put into place, Phil Grass and his 
                         welding crew of Tom Picard, Steve Nicholson, Jimmy 
                         Moore, Leo Bouchard, Willey McLeod, and Charlie Tapley 
                         took over and went to work under Jim’s supervision. 
                         Every 15 feet H beam was welded into place for the 
                         stays and was doubled up on each end of the 126 foot 
                         structure. Next, ½ inch x 3-inch angle iron was used as 
                         cross bracing every 20 feet in between the H Beam. All 
                         were placed in between the 36 inch I beam 5 feet 8 
                         inches on center. Next ½ inch x 1 inch pieces of pipe 
                         were cut and welded every 8 inches on the outside of 
                         each beam to provide for securing the decking to the I 
                         beam. Five hundred and four of these pieces were 
                         needed.
 
         
                             The 
                         placement of the decking on the bridge was the next 
                         step. On September 28th the decking in of 
                         th4e bridge commenced and took two days to complete. 
                         Two hundred fifty two pieces of hemlock planking 3 
                         inches by 6 inches x 10 feet in length was used for the 
                         decking of the bridge.     
                         The hemlock planks were drilled on each end and secured 
                         to the I beams by fastening with ½ inch x 5-inch 
                         carriage bolts. N.H Braggs donated Five hundred and 
                         four carriage bolts for this purpose. Kick plates were 
                         secured on each outside edge of the bridge. These were 
                         made up of 24 pieces of pressure treated lumber 2 
                         inches x 8 inches x 16 feet and were donated by 
                         Levasseurs Hardware. 
                              On October 6th the 
                         removable ramps were put into place on each side of the 
                         bridge. 
                              The ramps are 20 feet in length x 
                         20 feet in width and are also decked 
                         in with hemlock. These ramps will be removed each 
                         spring as  to restrict unwanted vehicle traffic. On 
                         October 19th heavy belted rubber was place 
                         over the area of the bridge where the lags from the 
                         Tucker would meet to prevent wear of the bridge 
                         decking. Railing supports and mounting hardware as well 
                         as 5/8 cable covered with rubber were installed to 
                         provide for a safety railing. Seeding of the stream 
                         banks near the bridge was done as well as covering it 
                         with hay to prevent any soil erosion. 
                                 The total length of the bridge 
                         is 166 feet, which includes the ramps. It is rated for 
                         a weight of 10 tons. Total estimated costs would have 
                         been well over $25,000 if the bridge had been 
                         constructed by a contractor.   
                          click 
                         here to continue on to the last page       
                          |